domi-ae.gr - Main Component
Euripus Bridge
Owner:
Ministry of Public Works
Location:
Chalkis
Construction:
HELLENIC TECHNODOMIKI SA
Construction Period:
1985 – 1993
Total Length:
695 m
Maximum Span:
215 m
Maximum Pylon Heigth:
90 m
Construction Method:
Balanced cantilever method
Deck:
Prestressed slab
Piers:
Reinforced concrete, variable box section
Foundation:
Piles
Services:
Complete design, camber design, technical support
Comments:
4th biggest span in Greece, probably the thinnest bridge worldwide, 1st cable-stayed bridge in Greece, assignment after competition